We are proud to have cooperated in the following projects and have been able to gain the satisfaction of our respected employers.
Employer: JAHAN PARS | |
2026 | Year of completion: |
Sarcheshmeh Copper Mine | Project |
Cooling Tower System Control commissioning | Activity |
Schneider | Services provided |
|
Employer: SAED |
|
|
2026 |
Year of completion: |
|
AZAR Oil & Gas refinery |
Project |
|
Commissioning the fire alarm system in the dormitory of Sarvak Azar Company |
Activity |
|
NSC |
Services provided |
Employer: OIEC | |
2023 | Year of completion: |
NGL3100 | Project |
F&G Commissioning for Non-industrial Buildings | Activity |
C-TEC | Services provided |
Employer: OIEC | |
2024 | Year of completion: |
NGL3100 | Project |
Control system commissioning for Heater Packages 300 & 700 | Activity |
Siemens | Services provided |
Employer: JAHAN PARS | |
2025 | Year of completion: |
Bushehr Petrochemical | Project |
Control system Commissioning in DCS, ESD, FGS, FACP, Waste Water Treatment, Chemical Injection … | Activity |
/NSCSUPCON/Siemens | Services provided |
Employer: JAHAN PARS | |
2024 | Year of completion: |
Urmia Petrochemical | Project |
Contorol system commissioning & Instrumentation installing (PAC Plant) | Activity |
SUPCON | Services provided |
Employer: EMACO | |
2023 | Year of completion: |
| Emotion Monitoring Tehran Oil Refinery’s Analyzer | Project |
Central industrial computer repair and Remote I/O, updating and programming | Activity |
OPSIS Analyzer | Services provided |
Employer: IRAN OFOGH (IOID)
| |
2021 | Year of completion: |
North Azadegan Oil Fields | Project |
Installation of I/O Server for SCADA system | Activity |
Citect SCADA | Services provided |
Employer: EMACO | |
2023 | Year of completion: |
Maroon Petrochemical RTO unit | Project |
Logic & HMI programming for control system, Instrumentation commissioning. | Activity |
Siemens Tia Protal v15 | Services provided |
Employer: KAYSON | |
2023 | Year of completion: |
Desalinize one million cubic meters of Bandar Abbas | Project |
Installation and implementation of precision tools, including the implementation of cabling and installation of precision tools | Activity |
Install instrumentation & control devices | Services provided |
Employer: TESCO | |
2022 | Year of completion: |
North Azadegan Oil Field | Project |
Installation & Commissioning of Historian server for SCADA system | Activity |
Citect Historical Server | Services provided |
Employer: Iran Gas& Water Developments | |
2022 | Year of completion: |
Arar Oil & Gas Field | Project |
Programming the F&G control system at the wellhead | Activity |
Fire Alarm Control Panel Solution F1 | Services provided |
Employer: JAHAN PARS | |
2022 | Year of completion: |
Arar Oil & Gas Field | Project |
Programming the control system of the RO unit, Instrumentation commissioning | Activity |
Omron PLC | Services provided |
Employer: ILAM Gas Refinery | |
2021 | Year of completion: |
ILAM Gas Refinery | Project |
Installation and addressing of F&G equipment, Commissioning | Activity |
ESSER by Honeywell system | Services provided |
|
Employer: Razi Industrial Design and Development Center
|
|
|
2021 |
Year of completion: |
|
Nakhl Asmari Petrochemical |
Project |
|
Control system engineering and programming, FAT and SAT testing, Commissioning for Acetaldehyde unit |
Activity |
|
ABB Freelanc DCS |
Services provided |
Employer: SAED | |
2021 | Year of completion: |
Azar Oil Refinery | Project |
Supply and installation of UPS package for the FGS system of the fire department building | Activity |
FARATEL | Services provided |
Employer: TESCO | |
2023 | Year of completion: |
North Azadegan Oil Field | Project |
Supply of TL105 Test Lamp for commissioning and calibration of UV, UV/IR and IR Flame Detectors | Activity |
Test lamp | Services provided |